Deployment

Deployment Strategy

Live deployment planned for Monday 26th September 2016 (according to Milestone delivery date).

 

Dependencies

New version of eRecruitment Successful applicants code is dependant on 'HRS089 eRecruitment Upgrade' eRecruitment Successfull applicants code being deployed first. HRS089 upgrade scheduled to be completed on Saturday 24th. The Successful Applicants code would next run on Monday 26th September at 1pm.

 

Communication

To be done by HR systems team to end users.

 

Deployment Checklists

Application checklist 

 

Component

Success Criteria

Project Stage Required (Agile)

Ok (Y/N)

Reviewed By (Date)

Outstanding Actions (Who)

Implementation Plan

Feedback from previous test implementations completed and successful full implementation undertaken for UAT

DSOR (Release 1-n)

Y

John Chan

30/07/2015

 

Implementation Risk Assessment

A risk assessment has been undertaken for the Implementation Plan and selected deployment dates. (e.g. roll back)

Roll back plan

ASOR (Release 1-n)

Y

John Chan

30/07/2015

 

System Design Specification (SDS)

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

 

 

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

System Description Document

Document complete and accurate.

 

Action: The Document must be copied to the Wiki

No SDD for the HR service

ASOR (Final Release  / Handover)

N/A

John Chan

30/07/2015

 

Scalability/Load Testing

Adequate load testing has taken place. The results have been recorded and analysed to ensure that the application will cope with the anticipated load.

No Load testing taken place as the numbers accessing UOE Self Service would not be increasing. Dev Tech mentioned that  when Self Service was implemented, Load testing had been done back then and would not need to be done again

 

ASOR (Final Release  / Handover)

N/A

John Chan

30/07/2015

 

Performance

The application has been tested against stated performance criteria. Performance has been assured by user and support staff testing.

No performance issues highlighted during UAT.

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Source Code

 

Source control must be checked out till go-live and checked-in after go live

Source code has been secured with VSS or other source control tool.

Where code is provided by a third party (e.g. supplier) it has been established who is responsible to maintain source code

DSOR (Final Release  / Handover)

N

John Chan

30/07/2015

Post Deployment Task: for JC/Pam S to check SVN.

Configuration Management Database

The relevant details regarding new or changed infrastructure components have been added to the configuration management database (This is currently maintained in the Change Control System)

No changes

ASOR (Release 1-n)

N/A

John Chan

30/07/2015

 

Change Control(s)

A change control entry has been created for the LIVE implementation request.

ASOR / (Release 1-n)

N

John Chan

30/07/2015

Morna to raise Change Control

Test Log Review

A review of the test log (JIRA) has taken place to ensure all required actions have been completed.   If this is not the case, then confirmation on criticality of outstanding issues and action plan for resolution is required.

To be reviewed during ASOR.

ASOR (Final Release  / Handover)

N

John Chan

30/07/2015

 

Production Management Handover

Handover to Production Management is completed and the team are in are in position to support the application post deployment.

ASOR (Final Release  / Handover)

N

John Chan

30/07/2015

 

No offical handover. JC to speak to AF to see if we want one.

Support Accounts

Read access accounts or update current read access accounts have been set up for support staff(requires business owner approval)

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Password Manager (InfoKeep)

InfoKeep has been updated with all relevant account details including external supplier  accounts

New functional account details entered in InfoKeep. Apps > HR

ASOR (Release 1-n)

Y

John Chan

30/07/2015

 

Environment comparison

Database comparison between TEST and LIVE (might be required before and after go-live)

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Client requirements

 

Does the application have specific client requirements, such as JVM/JRE versions, JInitiator?

If so have these requirements been raised with Desktop services

Wiki pages to be updated:

[1] https://www.wiki.ed.ac.uk/display/insite/Corporate+applications+with+client+based+requirements

[2] https://www.wiki.ed.ac.uk/display/insite/Client+side+requirements+for+corporate+applications

 

No new specific client requirements to access Online Paylips required from with HR Self Service.

ASOR (Release 1-n)

N/A

John Chan

30/07/2015

 

Technologies

Is there any new software or technologies involved? (Y/N)

If yes state any additional actions taken to ensure adequate handover to the production support team

No new client technologies involved.

ASOR (Release 1-n)

N

John Chan

30/07/2015

 

Access outside University

By default all web based applications are accessible outside University without use of VPN etc Wiki list

If not accessible from outside University this needs to be approved by Production Management.

 

ASOR (Release 1-n)

Y

John Chan

30/07/2015

 

Certificates

All changes to certificates or new certificates for this service have to be added to the certificate master list. The certificate master list is being managed by Applications Management This includes TEST and LIVE certificates and records type of certificate and expiry dates.

No changes to existing certificates being used.

ASOR (Final Release  / Handover)

N/A

John Chan

30/07/2015

 

 

Infrastructure checklist

 

Component

Success Criteria

Project Stage Required (Agile)

Ok (Y/N)

Reviewed By (Date)

Outstanding Actions (Who)

Technical Architecture Document(TAD)

Documentation complete and accurately reflects the environment subjected to UAT.

 

Action: TAD needs to be copied to Wiki

ASOR (Release 1-n)

Y

Tech Mgmt to review

 

Operational Document

Describes fully operational tasks and ongoing maintenance.This document should be fully populated and any missing sections or issues should be highlighted.

 

Action: TAD needs to be copied to Wiki

ASOR (Release 1-n)

Y

Tech Mgmt to review

 

Security

All security requirements, e.g. SSL encryption, IP based restrictions firewall requirements have been specified, tested and implemented in LIVE

ASOR (Release 1-n)

Y

Tech Mgmt to review

 

 

 

 

 

 

 

Patching

Ensure that all applications have an agreed patching schedule and this schedule is agreed with service owners. Different technologies have different patching strategies:

Oracle, Windows, Linux

No changes to current existing patching schedule

 

ASOR (Final Release  / Handover)

N/A

John Chan

30/07/2015

 

Infrastructure diagrams

All infrastructure diagrams are updated with newest server and infrastructure detail:

 

https://www.wiki.ed.ac.uk/display/insite/Server+Layout+%28Unix%29

 

and

 

https://www.wiki.ed.ac.uk/display/insite/Server+Layout+%28Windows%29

No changes to existing infrastructue required.

ASOR (Release 1-n)

N/A

John Chan

30/07/2015

 

Start/Stop scripts

Are Server Start-up/Shutdown scripts in place?

Including start-up procedure documented, enabled and tested.

No changes to existing infrastructue required.

 

ASOR (Release 1-n)

N/A

John Chan

30/07/2015

 

Ports

Port allocation file been updated:

 

https://www.wiki.ed.ac.uk/display/insite/Port+Allocation+on+Unix+Servers

No changes to port numbers.

ASOR (Release 1-n)

N/A

John Chan

30/07/2015

 

Backup and Recovery

All backups as noted in the TAD need to be confirmed operational.

 

A test recovery of user data needs to be done to validate the integrity of the recovery mechanism and process.

No changes to backup and Recovery procedures.

ASOR (Release 1-n)

N/A

John Chan

30/07/2015

 

DR Copy

DR copy to Edzell configured and tested(unless existing database which is already setup).

No DR testing required as part of this project as only software changes and application configuration settings

ASOR/Release1

N/A

John Chan

30/07/2015

 

Logs

For all logs the following is in place:

  • Logs are rotated and old logs are archived or deleted to ensure server space is not reached
  • In production only minimal levels of logging is switched on (debug may be adequate on DEV, but not on Production)

ASOR (Release 1-n)

N/A

John Chan

30/07/2015

 

High level Architecture Document (HLA)

If an HLA document exists this document has to be reviewed and moved/stored on the Tech Collab wiki section

No HLA document found.

ASOR (Final Release  / Handover)N/A

John Chan

30/07/2015

 

 

 

Support checklist

 

Component

Success Criteria

 Project Stage Required (Agile)

Ok (Y/N)

Reviewed By (Date)

Outstanding Actions (Who)

Support Agreement (including any charging arrangements)

 

A support agreement (SLA or OLA) is in place for any new applications – including any hosting or support charges.

 

Action: SLA moved to wiki:

 

https://www.wiki.ed.ac.uk/display/insite/SLA+repository+-+Applications+Management

No changes to SLA required.

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Time Recording Code

A Time Recording code for the application, if required, has been confirmed and set up.

Existing TR code to be used.

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Disaster Recovery and Business Continuity

Appropriate DR/BC provision is in place and has been fully tested. Application DR/BC details have been transferred to the DR Portfolio and DR level (1, 2 or 3) has been agreed

No changes to DR/BC required and therefore no testing required to be done.

ASOR (Release 1-n)

Y

John Chan

30/07/2015

 

Test Environment

An adequate TEST environment has been established for the application which may be used by support to test future changes prior to releasing these in the LIVE environment.

ASOR (Release 1-n)

Y

John Chan

30/07/2015

 

Hardware and Software Licensing

All required licensing is in place including maintenance/support arrangements with external suppliers.

Additional Self Service licences with Oracle have been purchased.

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Browser Compatibility

Browser compatibility has been tested and compatibility information updated

See

http://www.ed.ac.uk/schools-departments/information-services/services/computing/application-development/application-support/supported-web-browsers/browser-application

 for details

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Portal Compatibility

Portal compatibility, where required, has been confirmed the Portals Service Owner.

No changes to existing HR staff portal required.

 

ASOR (Final Release  / Handover)

N/A

John Chan

30/07/2015

 

Help Desk

The new application is recognised with the UniDesk (A business contact queue is defined where initial calls are raised with)

All helpdesk calls related to HR with be dealt with HR Systems Team.

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

User Guide Documentation

Appropriate documentation has been produced for users of the new application.

To be handled by HR Systems team

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Training Material

Training material, if required, has been produced and is of an appropriate standard.

To be handled by HR Systems team

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Demonstration or Walkthrough

Demonstration or walkthrough of the new application has taken place for other stakeholder.

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Deployment Date(s)

Agreed date has been confirmed that allows adequate time for completion of Acceptance Sign Off Review.

Planned deployment date at the top of this page.

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Deployment Resources

IS and business area resources required for deployment, including those needed for post implementation checking and sign off have been secured.

Project Manager to book resources via ASTA

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Deployment Ownership

Responsibilities for managing the go-live, including: comms with service owner and end users, ensuring go live timescales are met, managing issues arising and managing comms between all teams involved in go live.

Morna Findlay responsible from the IS side. Susan McLaren will manage comms between users and HR/

ASOR (Final Release  / Handover)

Y

John Chan

30/07/2015

 

Service Announcement(s)

A Service announcement has been raised with the agreed deployment date on the alert system:

 

http://reports.is.ed.ac.uk/alerts/

 

Service announcements should be raised by Project Manager 10 days before go live, but no later than 4 days.

ASOR (Release 1-n)

N

John Chan

30/07/2015

Morna Findlay to raise.

Web Sites and Other Document Sources

External and internal web sites have been reviewed to ensure that all application references are present, correct and up to date.

HR to update their website pages and are responsible for their content.

ASOR (Final Release  / Handover)

N/A

John Chan

30/07/2015

 

 

 

 

Project Info

Project
Online Payslips and P60s
Code
PPP002
Programme
Z. Payroll and Pensions (PPP) (closed)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
21-Oct-2014
Planning Date
n/a
Delivery Date
n/a
Close Date
26-May-2017
Overall Priority
Normal
Category
Discretionary