Support for the current version (11) will be ending so we need to move to the latest supported version.

 

From this work we will:

  • Migration of central databases to new infrastructure – APPSLIVE and NEWSLIVE
  • Have the databases able running on a fully supported version
  • Ensure that security issues are able to be address with the vendor

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2019 BLUE 530.0 days 531.0 days 0.0

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.