Migrate core databases to Oracle 12c - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2019 BLUE 530.0 days 531.0 days 0.0
Content
Status
Closed
Current Stage
Close
Start Date
Wednesday, 6 April 2016
Planning Date
Friday, 26 August 2016
Delivery Date
Tuesday, 4 December 2018
Close Date
Thursday, 11 April 2019
Project information
Project Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Session
18/19
17/18
16/17
15/16
Organisational Unit
IS Applications
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Compliance
Project Classification
Run
Funding Source
Core
Programme Priority
2
Overall Priority
Normal