This is a priority 2 compliance project

The funding of 197 days is split as follows using the "most likely" figure as this has been done previously: 118 days in 2016/17 for NewsLive and GenLive and 79 days in 2017/18 for AppsLive

 

Impact and Dependencies

The project will identify and retire schemas which are no longer used within the scope of the databases the project is addressing and migrate the live applications. As there are no database name changes involved in the majority of applciations , it is expected to have a low impact on applications using these schemas.

There is a dependancy on the COM029 project - COM029: Enterprise Data Warehouse (EDW) Delivery (secured)

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance