Impact
Priority and Funding
This is a priority 2 compliance project
The funding of 197 days is split as follows using the "most likely" figure as this has been done previously: 118 days in 2016/17 for NewsLive and GenLive and 79 days in 2017/18 for AppsLive
Impact and Dependencies
The project will identify and retire schemas which are no longer used within the scope of the databases the project is addressing and migrate the live applications. As there are no database name changes involved in the majority of applciations , it is expected to have a low impact on applications using these schemas.
There is a dependancy on the COM029 project - COM029: Enterprise Data Warehouse (EDW) Delivery (secured)