User Acceptance Test

1. Definition

 

The purpose of User Acceptance Testing (UAT) is to ensure that the solution by the project meets the functional and non-functional requirements specified in the business requirements. UAT may also identify issues that have not been specified in the BRD such as those relating to usability. UAT is the final step before rolling out the solution. UAT is typically carried out by end users in an environment that closely models the real world. A well-managed UAT process will give the Project Sponsor, project team and end users confidence that the solution being delivered meets the requirements.

 

This document outlines the plan for UAT of the project deliverables. This document is a high level guide and will initially be developed during requirements gathering as part of the Business Analysis stage. Detailed test scripts/cases will be developed as part of the UAT Plan and will be used to record the results of user testing. Testing itself and the formal recording of UAT results takes place during the Acceptance stage.

2. Roles and Responsibilities

 

Role                                                                 

Responsibilities                                                                                                                                                                                                                                   

 Name                             

Project Manager

·         Communication with the Business Assurance Coordinator to agree format and scope of UAT

·         Ensure acceptance criteria are agreed prior to commencing UAT

Chris Konczak

Technical Architect

·         Validation of UAT environment

Gordon McKenna

Testers

·         Execute test scripts/cases

·         Document test results

See table below

 

4. Test Participants

The following business owners are responsible for testing NEWS

Name             

 

Area Represented              

Testing Area of Responsibility                  

Jamie Morton/Paul Martin (Qlikview)

 

ADMISMI

 

Susan McLaren

 

HRMI

 

Emma Lyall/Jim Galbraith

 

ORGMI

 

Jamie Morton/Paul Martin (Qlikview)

 

STUDMI

 

Maureen Masson/Richard Mann

 

SPACEMART (EBISMI)

 

EFINARCH   Gordon Forbes  
Stefanie Hay   TELSMI   
UNIDESKMI   Andrew McFarlane  
       
       

 

 

5. Test Schedule

 

Activity                                                                                                                                                                                                                                                                                                

Responsibility                                                                                                              

Target Date           

Date Completed         

Confirm testers for UAT

Project Sponsor / Business Assurance Coordinator

 

 

Confirm test scenarios, test data and scripts/cases

Project Sponsor / Business Assurance Coordinator Business Analyst

 

 

Ensure UAT environment is configured for testing i.e. new functionality and test data is migrated to the TEST environment prior to the start of UAT

 

Project Sponsor / Business Assurance Coordinator Business Analyst Systems Analyst / Designer Technical Architect 

 

 

Oversee testing by UAT participants

Project Sponsor / Business Assurance Coordinator

 

 

All upgraded functionality and test data will be migrated to the test environment prior to the start of user acceptance testing.

 

6. Assumptions

 

  • The UAT environment will be available and fully configured ahead of the UAT.
  • The business team has reviewed and accepted functionality identified in the Business Requirements Document (BRD) and System Design Document (SDS).
  • Code walkthroughs/reviews have been completed by the Development Team and signed off as part of the Peer Project Build Review (PPBR)
  • Integration testing, including where relevant load and performance testing, has been completed and signed off as part of the Peer Project Integration Review.
  • Testers will test the functionality documented in the approved BRD (taking into account any changes in business requirement subsequently agreed by the Project Team)
  • Resources identified in this plan are available to conduct the UAT and address issues as they are raised by the test team.
  • [Business Analyst should record any additional assumptions here]

 

The Project Manager must notify the Project Sponsor if any of these assumptions are not correct before commencing the UAT.

Project Info

Project
Migrate core databases to Oracle 12c
Code
INF121
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
06-Apr-2016
Planning Date
26-Aug-2016
Delivery Date
04-Dec-2018
Close Date
11-Apr-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance