w/c 27th January 2020
  • Project Team meeting held 
    • confirmed eOPAS upgrade to Live could commence w/c 10th February
    • MJOG and ePortal upgrades would follow
    • Technical assistance from Technology Management available to assist with Spirometry issues - initial investigation scheduled for 30/01/20
  • MJog servers commissioned and now ready for installation

 

Andrew Stewart 27-Jan-2020
w/c 20th January 2020
  • Deployment Checklist commenced 
  • MJog sms txt messaging
    • New vm's for Test and Live have now been ordered 
  • Alerts - dates to be confirmed at project team meeting on 27/01/20
    • Go-CAB request submitted 
    • Service Alert submitted 
Andrew Stewart 26-Jan-2020
w/c 13th January 2020
  • MJog sms txt messaging
    • Unable to progress with the technical build - technical lead unavailable due to illness
  • eOPAS Upgrade
    • Health Surveillance UAT commenced
Andrew Stewart 26-Jan-2020
w/c 6th January 2020
  • Single Sign-On 
    • Project team have reviewed SSO technical requirements.  A number of points for clarification have been submitted to the supplier 
    • A conference call has been scheduled for Monday 13th January 
  • User Acceptance Testing 
    • Update from the business lead noting;

Andrew Stewart 06-Jan-2020
w/c 23rd December 2019
  • Single Sign-On 
    • Discussions on-going with the supplier and technical meeting scheduled for 8th January
  • User Acceptance Testing 
    • Test script update has not been circulated by the business lead as anticipated 
  • MJog Installation
    • The supplier has advised that it will not be possible to install the application on the Test environment - but only on the Live system.  Further clarity is being sought regarding this 
Andrew Stewart 06-Jan-2020
w/c 16th December 2019
  • Single Sign-On 
    • Discussions on-going with the supplier 
  • User Acceptance Testing 
    • Extract for CHPS tested and signed-off by the business lead 
    • Test script update being prepared by the business lead
  • Mjog sms txt messaging 
    • On-going discussions regarding the implementation and the possibility of installing a temporary version on the Test system for UAT
    • Commercials completed with the order form and signed contract being supplied by Occupational Health 
Andrew Stewart 20-Dec-2019
w/c 9th December 2019
  • Mjog
    • Confirmed license on eOPAS on both Test and Live environments 
    • Commercial documentation for MJog to be completed by Occupational Health - scheduled to be completed by the end of this week
    • The questions of data governance and Information security have been raised with both the project team and the supplier
    • Mjog have supplied details regarding content stored and data retention policy
  • Single Sign-On 
    • Commenced discussions with the supplier re SSO.  Currently awaiting feedback from the supplier
Andrew Stewart 11-Dec-2019
w/c 25th November 2019
  • Database Upgrade on Test 
    • Upgrade successfully registered by OH Business Lead 
    • Business Lead confirmed upgrade appeared to be ok 
    • HR interface tested and confirmed as functioning as expected 
  • Meeting with the business team resulting in project timescales being re-planned resulting 
    • UAT to be completed by 20/12/19
    • Go-Live scheduled for 03/02/20
  • ASTA updated to reflect new dates 
  • piccl prepared 
Andrew Stewart 26-Nov-2019
w/c 18th November 2019
  • Database Upgrade on Test 
    • Database upgrade delayed whilst query regarding the upgrade process (Re 107483) resolved with the supplier (raised 18/11/19)
    • Escalated the outstanding query (Re 107483) to the supplier on 19/11/19 
    • Advised on 20/11/19 - delay from supplier due to high volume of tickets 
    • Query (Re 107483) resolved on 20/11/19
    • Database upgrade completed on 20/11/19,
      • but version error displayed between the database (5.7.5.1) and the application (6.1.4.1) 
Andrew Stewart 26-Nov-2019
w/c 11th November 2019
  • System Upgrade 
    • Initial system tests successfully completed on the Test environment after the data refresh from Live 
    • Database upgrade delayed due to conflict on Technical Lead completing other system upgrade on timetabling - carried forward to next week 
  • Mjog
    • License costs received and forwarded to Occupational Health 
    • Currently awaiting guidance from Occupational Health on how to proceed
Andrew Stewart 26-Nov-2019
w/c 4th November 2019
  • eOPAS Upgrade 
    • Test system copied with a refresh of the Live system as on Thursday 7th November circa 16.46
  • Mjog
    • Contact re-established with supplier regarding integration with eOPAS
  • Test Script 
    • A spreadsheet is being compiled and will continue to be worked on 
Andrew Stewart 08-Nov-2019
w/c 14th October 2019
  • Project Planning 
    • Project team meeting held to review the project brief. 
      • Signed off by Business , Technical Lead, Enterprise Architecture
  • JIRA
    • project code created 
    • project activity logged in JIRA
Andrew Stewart 17-Oct-2019
w/c 30th September 2019
  • Commenced Project Brief
Andrew Stewart 01-Oct-2019
w/c 23rd September 2019
  • Project Planning 
    • meeting with business team to clarify
      • project objectives and deliverables
      • project timescales 
  • Project Resourcing 
    • Dev Tech resource assigned to the project 

 

Andrew Stewart 01-Oct-2019
w/c 16th September 2019
  • Project Initiation 
    • Prepared project start-up submission documentation.  Approved by Project Sponsor 
    • Request to commence project approved by WIS
  • Project Planning 
    • Prepared outline project plan based on previous estimate
Andrew Stewart 01-Oct-2019

Project Info

Project
eOPAS Upgrade
Code
HAS008
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
07-Feb-2020
Close Date
06-Mar-2020
Overall Priority
Normal
Category
Discretionary