w/c 25th November 2019

  • Database Upgrade on Test 
    • Upgrade successfully registered by OH Business Lead 
    • Business Lead confirmed upgrade appeared to be ok 
    • HR interface tested and confirmed as functioning as expected 
  • Meeting with the business team resulting in project timescales being re-planned resulting 
    • UAT to be completed by 20/12/19
    • Go-Live scheduled for 03/02/20
  • ASTA updated to reflect new dates 
  • piccl prepared 

Project Info

Project
eOPAS Upgrade
Code
HAS008
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
07-Feb-2020
Close Date
06-Mar-2020
Overall Priority
Normal
Category
Discretionary