w/c 23rd December 2019

  • Single Sign-On 
    • Discussions on-going with the supplier and technical meeting scheduled for 8th January
  • User Acceptance Testing 
    • Test script update has not been circulated by the business lead as anticipated 
  • MJog Installation
    • The supplier has advised that it will not be possible to install the application on the Test environment - but only on the Live system.  Further clarity is being sought regarding this 

Project Info

Project
eOPAS Upgrade
Code
HAS008
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
07-Feb-2020
Close Date
06-Mar-2020
Overall Priority
Normal
Category
Discretionary