w/c 11th November 2019

  • System Upgrade 
    • Initial system tests successfully completed on the Test environment after the data refresh from Live 
    • Database upgrade delayed due to conflict on Technical Lead completing other system upgrade on timetabling - carried forward to next week 
  • Mjog
    • License costs received and forwarded to Occupational Health 
    • Currently awaiting guidance from Occupational Health on how to proceed

Project Info

Project
eOPAS Upgrade
Code
HAS008
Programme
Health & Safety (HAS)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Candice Schmid
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
20-Sep-2019
Planning Date
18-Oct-2019
Delivery Date
07-Feb-2020
Close Date
06-Mar-2020
Overall Priority
Normal
Category
Discretionary