Updates 11-Nov-13

Last approved estimate 36 days.

Now need 46 days

PM/Governance 12 days

Planning 6 days

Do It  and Check It  16 days

Release 7.5 days

Data Transfer Investigation 4 days

Closure 0.5 day

12+6+16+7.5+4+0.5 = 46 days

If less is required it will not be charged.

Project Info

Project
Corporate Planner
Code
FIN092
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Lorna M McLoughlin
Current Stage
Close
Status
Closed
Start Date
19-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Dec-2013
Programme Priority
2
Overall Priority
Higher
Category
Compliance