FIN092 Corporate Planner Progress 19-Sep-13
| Progress | Date Completed | % Complete | Comment |
| Machine and VM Set up request ITI + asked re Refund- REQUEST | 23-Sep-13 | Cpt | No refund available, but can re-configure existing machine |
| Design Technical Architecture Document (TAD) | 0 | Now planned for 19-27 Sep | |
| Machine and VM Set up | 19-Sep-13 | 95% (2 hours left) | Outlook call verify VM costs - before was estimated costs |
| Request Firewall | 13-Sep-13 | Cpt | |
| Preparation for LIVE + scrip prep | 17-Sep-13 | Cpt | Ready for Go Live on 20th |
| Handover and Deployment checklist | 0 | Delay Document next week 23-27 Sep | |
| Support Live | 0 | Support starts next week | |
| Deploy LIVE - Consultant | Plan 20-Sep-13 | 0 | Booked agreed 20th afternoon |
| Operation Documentation | to be rescheduled |
Last fortnight
- Gillian was off sick at the start of the project
- IS Apps raised priority on VM server set up, so most of the work has been complerted between 13-19th Sept
- But other tasks have had to be delayed until next week
- Generally good progress has been made
Next week
- document what has actually been completed
- documentation for project e.g. TAD
- Operations document
- Deployment checklist may be delayed further
Plan can be viewed here: Project Plan