TEST environment required or not?

Against TEST

  • Account Ability do not believe we need a test environment however if the expectation is that UOE will be carrying out patching activities upgrades etc we would recommend a test environment to carry out this work on before progressing to live. It all depends on the support arrangements after go live and our involvement in subsequent work.
  • If the Corporate Planner system can accept longer periods of downtime or risk during upgrade/patching activities then it may be determined that a test environment is not required.

   Actual Costs for VM Server

  •  Here are the indicative 5 year costs for the 2 live VM servers. Breakdown below for your information.
    • ITI will confirm the actual costs in I130823-0594.
  • App Server = £1730
    • (memory £1517, 100GB Disk £127, 100GB backup £86)
  • DB Server  = £2993
    • (memory £1818, 550GB Disk £700, 550GB backup £475)  

For TEST

  • The latest upgrade caused an outage on the LIVE system, this may have been avoided if this was carried out in a TEST environment first.
    • For example a test environment would allow the upgrade to be tested out, verify upgrade/patching process, calculate downtime, allow users to test the upgraded environment.
  • The request for a refund on the existing machine will not be provided, details can be found in the Unidesk call I130823-0594\02 where we included the request for new VM.
    • The VM Server can be re-used for Test, which will mean no other VM Server will be needed.
    • If we go down that route an estimate will have to be reviewed ahnd included to reconfigure the Test VM Server.

 

 

Project Info

Project
Corporate Planner
Code
FIN092
Programme
Finance (FIN)
Project Manager
Anne Mathison
Project Sponsor
Lorna M McLoughlin
Current Stage
Close
Status
Closed
Start Date
19-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Dec-2013
Programme Priority
2
Overall Priority
Higher
Category
Compliance