Business requirements gathering, including consolidation of existing radiation User Stories plus 2 x User Groups workshops to gather bio-hazard User Stories
Foundations phase to include technical set-up, User Story estimation and prioritisation
3 x 2-week development iterations
1 x 2-week BI/reporting iteration
Maintenance period (to address live issues/feedback)
Closure
Resources Skills and Cost
IS Applications resources
Project Manager (1-2 days per week)
Business Analyst (2 days per week)
Development Lead/Agile Coach (1 day per week)
2 x Coldfusion Developers (5 days per week during development iterations)
1 x BI Developer (5 days per week for a 2-week period towards the end of development)
Tech Rep (for initial environments set-up then 0.5 per week)
Support Rep (up to 0.5 day per week)
Business resouces
Product Owner (2 days per week)
Business area specialist for radioactivity (2 days per week)
Business area specialist for bio (2 days per week)