Iteration 1.2

Planned Stories

Please note that stories CSG005-1, CSG005-38, CSG005-39, CSG005-21 and CSG005-50 were brought forward from iteration 1.1 as they were not fully 'done' .  Only 4 of their 15 points is actually within this iteration.

Actual Stories

Actual velocity (story points delivered) = 16 points (calculated as 27 minus the 11 points actually delivered in iteration 1.1)

 

What went well?

  • Minor technical issues in this iteration unlike iteration 1

 

What didn’t go so well?

  • Possibly too much time spent on automated tests at the beginning of the iteration
  • Easter hols falling within the iteration

 

Anything to do differently?

  • None

Project Info

Project
RETAIN Enhancements
Code
CSG005
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Dawn Holmes
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
26-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Overall Priority
Normal
Category
Compliance