Iteration 1.1

Planned Stories

 

Actual Stories

Actual velocity (story points delivered) = 11 points

End of Iteration Review

What went well?

  • Migration from CF9 to CF10.  All went pretty smoothly
  • Requirements gathering

What didn't go so well?

  • Issues with automated tests which distracted from planned development
  • Resource conflicts for lead developer which distracted from planned development
  • Set-up of live server via UNIX took much longer than planned
  • Work on 'New PI role' uncovered a number of issues with role permissions that needed to be addressed.  This added another 3 points of work to the iteration via story CSG005-50
  • DIdn't get through planned work (mostly due to issues as described above) but the outstanding stories were almost 'done' so only carrying forward 4 points (i.e. 11 points out of 15 completed)

What will we do differently next time?

  • n/a - will continue as for this iteration as the issues preventing progress are now (hopefully) resolved

Actions

  • New enhancement story for clearly displaying dual-role on user admin screens - done 27/03/15
  • New story for removing PI role - done
  • New story for unlinking substance from a project - done
  • Mike/Jonny to speak to management about server set-up process within APP004 project

 

 

Project Info

Project
RETAIN Enhancements
Code
CSG005
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Dawn Holmes
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
26-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Overall Priority
Normal
Category
Compliance