Plan
Document Sign-off
Name | Role | Date signed off |
---|---|---|
David Fergusson | Project Sponsor | |
Andrew Todd | Project Manager | |
Maurice Franceschi | Programme Manager |
Work/Task Breakdown
The following phases will be undertaken;
Initiation: Including development of project brief and approval process.
Planning: Further define scope, produce plan and wider project documentation, develop dedicated project team in SRA and Colleges.
Priority and Funding
This discretionary project has been classified as priority 1 (HIGH)
Funding of 50 days, 35 within 2017/18 and 15 within 2018/19.
Impact and Dependencies
There is a dependency on the Euclid Student Records System being available and positioned to deal with any recruitment brought about through clearing.
Background
The University plans to enter UCAS clearing again this year with places being available for a small number of students from particular target groups in Scotland; for RUK students for specific degree programmes; and for International students.
Scotland
Version Control
Date | Amendments |
---|---|
17/05/18 | First draft for discussion |
Final version |
Project has been suspended awaiting confirmation from Bayes/School of Informatics regarding academic contributors.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
December 2019 | BLUE | 0.0 days | 0.0 days | 0.0 |
Estates Computer-Aided Facilities Management Systems Optimisation project seeks to optimise the CAFM solution in line with University of Edinburgh Estates and IS business goals.
Following delivery of an Options Appraisal (EST121) this project is expected to undertake a detailed analysis of the agreed (3) short listed options and deliver:
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
September 2019 | GREEN | 108.0 days | 122.4 days | 45.6 |
This project covers all tasks and evidence gathering required for the SDi Service Desk Certification Programme.
SDI Service Desk Certification Programme wiki:
https://www.wiki.ed.ac.uk/display/USDSDC/SDC+Home
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
April 2018 | GREEN | 0.0 days | 0.0 days | 0.0 |
DTP017 – Deployment of MAC Desktop to Labs
Project Brief
Document Sign-off
Name |
Role |
Continue to review and develop connectivity both wired and wireless within locations which are utilised by students. This has so far been focussed primarily on NHS locations, however other locations which would be of benefit to the College can be added in due course.
Current project status
Report Date | RAG | Budget | Effort Completed | Effort to complete |
---|---|---|---|---|
November 2019 | GREEN | 0.0 days | 0.0 days | 0.0 |