Plan

The increase in voice user interface and associated devices by the University's key demographic gives us an opportunity to positively impact user engagement and offer a better customer experience. Google estimates that 20% of its queries on its mobile app and Android devices are voice searches and the forecast is that 50% of searches will be voice searches by 2020. The 16-25 age group have been identified as early adopters in the use of the technology.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2018 BLUE 0.0 days 0.0 days 0.0

The Common Sense

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2018 GREEN 0.0 days 0.0 days 0.0

Priority and Funding

This project has a priority of 2.

The Enterprise APIs Programme has a priority of 1.

The project is funded from the Digital Transformation Portfolio.

Impact and Dependencies

The API functionality delivered by this project will support delivery of the following projects by exposing student data that can be used by developers within those projects:

Background

See Overview of Programme for further detail.

Scope

This project (DTI024) will deliver additional Student Record APIs or extend the collection of methods on the initial release of the Student Record API (delivered by DTI015) in order to support delivery of the DTI011 and SAS002 projects by exposing data required by these projects:

Document Sign Off

Document Sign-off

 

Name

Role

Date signed off

Dave Graham

Project Sponsor

Small project to produce policy briefing on human rights in investment, including linking to modern slavery work, with proposals on way forward.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
July 2018 GREEN 0.0 days 0.0 days 0.0

Document Sign-off

Name Role Date signed off
David Fergusson  Project Sponsor  
Magdalena Getler  Project Manager 05/02/2018
Maurice Franceschi  Programme Manager  

Service providers and the research  community 

This project is a review of the communications issues to students from EUCLID. It is not likely to have SSP development involvement, and has been created as a project to enable the plan, status and project work to be visible to senior SSP management.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2017 AMBER 0.0 days 0.0 days 0.0