Title Report Date Time Cost Scope Overall Change
Report for January 2020 (Interim) January 2020 GREEN GREEN GREEN GREEN No Change
Report for December 2019 December 2019 RED GREEN GREEN RED
Report for November 2019 November 2019 GREEN GREEN GREEN GREEN No Change

Project Info

Project
MyEd Continuous Improvements
Code
WPS004
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Stratos Filalithis
Current Stage
Initiate
Status
In Progress
Project Classification
Grow
Start Date
06-Sep-2019
Planning Date
13-Dec-2019
Delivery Date
17-Jan-2020
Close Date
08-May-2020
Programme Priority
2
Overall Priority
Normal
Category
Discretionary