Report for January 2020 (Interim)
- Report Date
- January 2020
Achievements this period
- RED development resourcing issue which was the result from a conflict with SAS020 has now been resolved. Resource has been assigned to commence the development iterations from 03/02/2020.
- Milestones have been agreed and set
Issues
- None
Next Steps
- Brief signoff can now be achieved
- Foundation iteration meeting to prepare for Iteration 1 to start
Milestones
| Planning sign off | 17-Jan-2020 |
| Foundation complete | 31-Jan-2020 |
| Iteration 1 complete | 21-Feb-2020 |
| Iteration 2 complete | 20-Mar-2020 |
| Iteration 3 complete | 17-Apr-2020 |
| Iteration 4 (maintenance) complete | 01-May-2020 |
| Deploy to LIVE | 05-May-2020 |
| Closure | 15-May-2020 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days