Report for November 2019
- Report Date
- November 2019
Achievements this period
- Project startup meeting held with team to discuss the approach and next steps
- Brief written with user stories (JIRAs) taken from DTI044 and moved into WSP004
- User stories mapped to objectives and deliverables
Issues
- Resourcing for the developer has been delayed as SAS020 had requests in for the developer before the Asta project request for WSP004 was created. This has resulted in WSP004 waiting for the milestones in SAS020 to be set before the resourcing can be approved.
Next Steps
- Brief to be completed with the user stories mapped to the objectives and deliverables and sent round for approval
- Resourcing to be confirmed
- Foundation iteration to be completed so developer is ready to start coding in January
Milestones
| Planning sign off | 13-Dec-2019 |
| Foundation complete | 20-Dec-2019 |
| Iteration 1 complete | 24-Jan-2020 |
| Iteration 2 complete | 14-Feb-2020 |
| Iteration 3 complete | 06-Mar-2020 |
| Deploy to LIVE | 18-Mar-2020 |
| Iteration 4 (maintenance) complete | 01-Apr-2020 |
| Closure | 10-Apr-2020 |
- Approved budget
- 50.0 days
- Activity this month
- 3.5 days
- Activity this year
- 3.5 days
- Activity to date
- 3.5 days
- Estimate to complete current year
- 48.0 days
- Estimate to complete future years
- 0.0 days