Impact

Priority and Funding

This is a normal priority discretionary project

 

Impact and Dependencies

We assume that the work being done in Core Systems and Service Excellence will continue along the published timelines.

There is a current dependency on the developer as they are also the lead developer on the SAS020 New MyEd Finance Channel project.

 

Project Risks

Risk that application resources are lost to a higher priority project AMBER Retain Paul Mcnulty
Risk of budget over-spend GREEN Reduce Tim Gray
Risk with Business availability for testing GREEN Reduce Stratos Filalithis
Risk that all desired user stories may not be completed due to 50d budget AMBER Retain Duncan MacGruer
Risk on resources from end of February due to potential strike action AMBER Retain Paul Mcnulty
Risk on budget by including TestRail for UAT GREEN Retain Duncan MacGruer

Project Info

Project
MyEd Continuous Improvements
Code
WPS004
Programme
ISG - Web and Portal Services Programme
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Stratos Filalithis
Current Stage
Initiate
Status
In Progress
Project Classification
Grow
Start Date
06-Sep-2019
Planning Date
13-Dec-2019
Delivery Date
17-Jan-2020
Close Date
08-May-2020
Programme Priority
2
Overall Priority
Normal
Category
Discretionary

Documentation

Plan