Project Brief

Document Sign Off

Name Project Role Date Signed Off
Scott Rosie Project Sponsor 12/12/2019
Stefan Kaempf Head of Production Management 11/12/2019
Neal Beaton TTU Systems Officer (Project Team Member) 11/12/2019
Mark Dobbing IS Applications - Dev Tech (Project Team Member) 11/12/2019
Gavin Pennycook IS Applications - Development (Project Team Member) 10/12/2019
Brian Denholm IS Applications - Applications Management (Project Team Member) 11/12/2019
Mark McGowan IS Applications - Technology Management (Project Team Member) 11/12/2019
Jamie Thin TTU Programme Manager (Project Team Member) 09/12/2019
Ken Miller Project Manager (Project Team Member) 09/12/2019
Suran Perera Senior Supplier - IS Applications Applications Management  11/12/2019

 

Project Info

Project
Timetabling Service - Scientia Enterprise Timetabler Annual re-build & Rollforward
Code
TTU020
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
Ken Miller
Project Sponsor
Scott Rosie
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
04-Oct-2019
Planning Date
25-Oct-2019
Delivery Date
20-Jul-2020
Close Date
30-Oct-2020
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation

Plan