Overview

Background

Annual project to deliver annual software upgrade and  other  small essential changes to maintain a robust and sustainable service.

To upgrade the Scientia Exam Scheduler (ES) product from ES v3.5.9 to ES v3.5.11

- this will move the Exam Scheduler product to the latest release to ensure the product stays fully supported by Scientia, and to deliver small enhancements to the product.

The upgrade will be applied to DEV and TEST , then regression testing will be done by business users in the Exams team before applying the upgrade to LIVE.

The upgrade tech tasks will be done remotely by the supplier tech consultancy team (Scientia).

ISG Project manager will co-ordinate the upgrade tasks and testing.

Testing will include testing of the upgraded product plus feeds to downstream systems - Calsync for Exams , BI Reporting and Exam web timetables.

The project activity has to be squeezed into the Exams business cycle between the end of the Exam Scheduling for the August 2019 resits , and before the start of scheduling for the main Dec 2019 exam diet in early Sept 2019

 

Scope

It is proposed that there are 3 work packages for this project:

1] WP1 - Upgrade Exam Scheduler from ES v3.5.9 to ES v3.5.11 in Sept 2019

2] WP2 - Deliver small enhancements to the connector from Student systems to Exam Scheduler ( Scientia Tech consultancy) in Oct 2019

3] WP3 - Deliver small changes / complete tasks as identified in the 10 JIRAs carried over from the SEP SAS005 project, include testing of cleardwon script to do deletion of old data to improve performance of LIVE system

JIRA    Summary ( from SEP SAS005) :

TTU019-10    Exam Scheduler LIVE - Performance issue - check server logs and resources on the servers - app and db servers

TTU019-9    Instructions for users after Windows 10 upgrade

TTU019-8    Data mapping change to Extra writing time - Add new Suitability-key = 100 (100%)

TTU019-7    Small Room tag error in LIVE <5 and <25

TTU019-6    Diet 30 to be redundant

TTU019-5    Exam Scheduler v3.5.9 - slow response times in LIVE

TTU019-4    Exam Scheduler LIVE > Tools > Metrics > Back To Back Students - Execution Timeout Expired

TTU019-2    Exams db views - Handover to BAU - TBC- IS S/W Dev team or SSP Dev team - Developer access to Bamboo / GIT tool for the UoE-exam-timetables db views on exams-db-dev and exams-db-test

TTU019-3    New Connect workflow job to filter students by future exam diet, and only import  student changes for specific exam periods ( diets) 

TTU019-1    'Fixed start date' for CHEM09009 not updated when fresh data imported as part of ES-05A-Exam-Requirements-Selector Connect Job   

All 3  work packages will require extensive testing by business users in the Exams Office in TEST , ahead of deploying changes to LIVE

 

Objectives and Deliverables

No. Description

Priority

MoSCoW

Owner
O.1. WP1 - Upgrade Exam Scheduler from ESv3.5.9 to ES v3.5.11 with minimum downtime and minimum disruption to business as usual activities Must Have All
D.1.1 Upgrade DEV and TEST Must Have Scientia Tech team
D.1.2 Complete Integration testing  in TEST - of end-to-end solution - incl Incoming data feeds, Exam Scheduler application and downstream data feeds  Must Have IS production team
D.1.3 Complete UAT  in TEST - regression test of existing functionality Must Have Exams team
D1.4 Complete UAT  in TEST - new functionality    
D.1.5 Upgrade LIVE Must Have Scientia Tech team
O.2 WP2 - Deliver enhancements to Connect workflows for the connector from Student Systems to Exam Scheduler Should All
D.2.1

Complete build of additional prompts added to Connect – ES-03 Import Students to allow for:

  • exam period selection
  • update of all details of all students who sit exams during the selected period
  • update of ‘name’ of all students who sit exams during the selected period  
Should Scientia Tech team
D2.2 Complete integration testing in TEST - connection to Student Systems Should IS production team
D2.3 Complete UAT in TEST Should Exams team
D2.3 Deploy to LIVE Should Scientia Tech team
O.3 WP3 - Test cleardown of historic data to improve performance, and do cleardown in LIVE Should All
D3.1 Run Scientia cleardown script with date defined by the Exams Office, sign-off in TEST , then apply to LIVE Should UoE project team
O.4 WP3 - Complete work on non-urgent JIRA backlog carried over from SEP SAS005 project Could UoE project team
D3.2 Work through the 10 JIRAS carried over from SAS005 Could UoE project team
       

Benefits

WP1 - Upgrade to ES v3.5.11 - These 4 features in the new release will provide specific benefits to the UoE

Snippet from ES v3.5.11 release notes

WP2 - Improvements to the Student Systems connector should improve the quality of student data in Exam Scheduler and more tightly manage when data is imported in to Exam Scheduler. The improvement  to how  Student name changes are handled - should reduce distress caused to students when they have changed their name and it has not been updated in Exam Scheduler.

WP3 - Cleardown of old data from previous year should improve performance of the Exam Scheduler system - as advised by Scientia 

Success Criteria

WP1, WP2 and WP3 are successfully delivered with no degradation of the service to Students and Staff 

 

Project Milestones

Build    WP1 - Upgrade DEV & TEST to ES v3.5.11    20-Aug-2019 (Done)
Plan    End of Planning    06-Sep-2019  
Accept    WP1 - Complete system testing and UAT in TEST    09-Sep-2019 (Done)
Accept    WP1 - Acceptance sign-off for Upgrade    10-Sep-2019 (Done)
Deliver    WP1 - Upgrade LIVE to ES v3.5.11    18-Sep-2019 (Done)
Deliver    WP1 - Deployment review    02-Oct-2019 
Build    WP2 - Complete build of Connect workflow changes    31-Oct-2019
Build    WP3 - Work through JIRAS    31-Oct-2019
Accept    WP2 - Completion of Integration testing and UAT    15-Nov-2019
Accept    WP3 - Test and deploy changes for each JIRA    15-Nov-2019
Deliver    WP3 - Complete JIRAS    19-Nov-2019
Deliver    WP2 & WP3 - Deploy to LIVE    20-Nov-2019
Deliver    WP2 & WP3 - Deployment review    22-Jan-2020
Close    Project Closure    31-Jan-2020  

                                                          

AttachmentSize
Image icon Snippet from ES v3.5.11 release notes42.01 KB

Project Info

Project
Scientia Exam Scheduler Upgrade
Code
TTU019
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
James Thin
Project Sponsor
Scott Rosie
Current Stage
Plan
Status
In Progress
Start Date
19-Jul-2019
Planning Date
30-Aug-2019
Delivery Date
18-Sep-2019
Close Date
31-Jan-2020
Overall Priority
Normal

Documentation

Plan