Priority and Funding

This is a compliance project which is funded from the core TTU Programme. Although set to NORMAL at the end of planning, a request will be submitted to raise the priority to HIGHEST as there is a small window in the Timetabling Unit calendar for this upgrade to be applied without impact. There are likely to be demands on the secured resources from other projects. Resources with Timetabling knowledge are limited in Development Technology and Development.

A budget of 175 days was initially estimated for this project, 80 days in 2017/8 and 95 days in 2018/19. However, due to delays in starting this project, the balance was adjusted to a greater number of days in 18/19. The budget is now 27 days in 2017/18 and an estimated 156 days in 2018/19, a total of 183 days.

 

Impact and Dependencies

This project has the potential to interfere with other Timetabling projects. To mitigate this, is has been agreed to use the approach adopted in TTU010 during the last upgrade, namely the build of a set of parallel timetabling servers with Scientia v3.14 software and to switch over to these from the existing servers.  

To ensure that any essential changes applied to the v3.12 environments are carried over to the new 3.14 environments, an appropriate change control process, to last for the duration of the project, will be agreed between the project team, the production team and the timetabling team.

TTU016 Timetabling Service Annual Re-build and Roll Forward to 18/19 will close during the same period as this project. And a new project TTU018 Timetabling Service Annual Re-build and Roll Forward to 19/20 will start. So careful co-ordination of the activities across projects will be required, particularly around the early SDB and Web Apps tasks for 19/20.

SAS005 Exam Timetabling and SAS014 MVM Room Booking will require some of the same resources over the same period, as will MLE004 Lecture Recording Expansion Phase. Project Managers will need to be aware of plans and work with the appropriate resourcing managers to resolve any conflicts. Any which cannot be resolved will be escalated as per the process in place.

There needs to be an awareness of the changes being considered by SAS0013 Comprehensive Student Timetabling and SAS014 Medical School Room Booking System Implementation and any decisions made regarding the way forward.

Technical skills and timetabling knowledge required will mean that some of the same resources will require to work on all these projects.

 

Project Risks

Ref Title Initial Risk Current Risk Status Management Approach Risk Owner
1 Risk of extra effort to support integration testing and acceptance sign-off RED AMBER Open Reduce Mark Lang
2 Impact from strike action GREEN GREEN Closed Retain Susan Duff
3 Post login plugin may not work with v3.14 RED RED Open Reduce Bill Lee
4 v3.14 introduces new issues AMBER AMBER Open Retain Scott Rosie
5 Narrow window in business calendar for upgrade AMBER AMBER Open Reduce Susan Duff
6 Differences between the new DEV/TEST/LIVE/MOD environments when build completed GREEN GREEN Open Reduce Mark Dobbing
7 Changes to the LIVE environment are not mirrored in the new environment AMBER AMBER Open Reduce Suran Perera
8 Image creation fails AMBER AMBER Open Reduce Stefan Kaempf
9 Availability of Development resources RED RED Open Reduce Iain Fiddes
10 Availability of Dev Tech resources AMBER AMBER Open Reduce Mark Lang
11 Existing servers and services running may mask incomplete deployment to new infrastructure GREEN GREEN Open Reduce Mark Dobbing
12 Ongoing Timetabling and Room Booking development could impact scope of this project RED GREEN Open Reduce Scott Rosie
13 Testing doesn't identify issues with the build or release AMBER AMBER Open Reduce Scott Rosie
14 Deployment plan incomplete AMBER AMBER Open Reduce Suran Perera
15 Impact on Annual Timetabling Service Re-build and Roll Forward from any delay to the upgrade RED RED Open Reduce James Thin
16 Availability of Timetabling Unit Resources GREEN GREEN Open Reduce Scott Rosie
17 3.14 performance is unacceptable AMBER AMBER Open Reduce Stefan Kaempf
18 Interfaces may not be available for testing AMBER AMBER Open Reduce Scott Rosie
19 Change from 1 to 3 Web Servers causes problems GREEN GREEN Open Reduce Mark Dobbing

 

Project Info

Project
Timetabling Service - Scientia Upgrade to EF v3.14 and move to new servers
Code
TTU017
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
James Thin
Project Sponsor
Scott Rosie
Current Stage
Deliver
Status
In Progress
Project Classification
Run
Start Date
01-Dec-2017
Planning Date
02-Jul-2019
Delivery Date
12-Nov-2019
Close Date
31-Jan-2020
Programme Priority
2
Overall Priority
Highest
Category
Compliance

Documentation