Organisation

Work/Task Breakdown

IS Applications - roll-forward data and interfaces

TTU - business analysis and testing

 

Apprpximate split:

Project services - 42 days

Development services (CSG) - 33 days

Developlemt Technology - 44 days

Production management - 10 days

All teams - 34 days

 

 

Resources Skills and Cost

Estimate 180 days IS Apps effort

Project Info

Project
Timetabling Service Annual rebuild and Roll-Forward to 16/17
Code
TTU012
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
Morna Findlay
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
18-Sep-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Oct-2016
Programme Priority
1
Overall Priority
Higher
Category
Compliance