Completion Report

Project Summary:

. The project had a short timeline to accomplish two tasks

D1 Environment separation for Edinburgh - moving to its own Application and Database servers in LIVE and TEST

D2 Review of hosting with recommendations for future changes. These recommendations woudl be prioritised and estimated.

 

These have been delivered, so that USD, Service Management and Applications can decide what to do next.

Analysis of Resource Usage:

Staff Usage Estimate: 20 days

Staff Usage Actual: 45 days

Staff Usage Variance: 125%

Other Resource Estimate: 9000 days

Other Resource Actual: 0 days

Other Resource Variance: -100%

Explanation for variance:

.The initial technical estimate did not fully take into account the full scope of the work involved.

 

The consultancy costs are zero as confirmed by Project Sponsor.

 

Recommendation Report

Key Learning Points:

.A dedicated, focussed, co-located, collaborative team can get a lot done, well in a short time.

Outstanding issues:

.none

Project Info

Project
Review of UniDesk Infrastructure
Code
SMI011
Programme
ISG - IT Service Management (SMI)
Project Manager
Maurice Franceschi
Project Sponsor
Alex Carter
Current Stage
Close
Status
Closed
Start Date
04-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
31-Aug-2015
Programme Priority
5
Overall Priority
Normal
Category
Discretionary