Service Management User Documentation Planning

Things that should be covered by the training materials/courses, including relevance to 1st/2nd line and level of the topic.

 

Topic1st line2nd lineLevel of topic
Using a Standard SolutionYesYesBasic use
Creation of Standard Solutions-YesMedium
Checking and Linking to known-errors/problemsYesYesMedium
Creation of problem records from incidents-YesMedium
Problem management, turning into known errors-YesAdvanced
Initiating requests for changeYesYesBasic use
Actions for standard changes (Release)YesYesBasic use
Processing complex or emergency changes-YesAdvanced

 

Project Info

Project
TOPDesk Upgrade to v 5
Code
SMI002
Programme
ISG Portfolio Projects (OTHISG)
Project Manager
Sue Woodger
Project Sponsor
Bryan MacGregor
Current Stage
Close
Status
Closed
Start Date
04-Oct-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Oct-2013
Programme Priority
1
Overall Priority
Higher
Category
Discretionary