Organisation
Work/Task Breakdown
1/ Planning
- Prepare project brief
- Prepare project estimate
- Plan
2/ System Design
- Technical Architecture Document
3/ Build
- Request 20 Servers from ITI
- Build/Configure
- Move Java to OpenJDK
- Use Puppet to build severs
- Upgrade SITS on 1 server and clone the environment to the remaining 11
- Build DEV/Test/TRN/Live/Dust
- Produce Roll Back Plan
- Test and decide solution for Integrator
4/ Integration
- Integration testing between EUCLID & Downstream systems/components/feeds
- Performance testing
5/ Acceptance
- Sign off each build stage
- Handover to Production (Prod Deployment Checklist)
6/ Deployment
-
Implementation Plan detailing the SwitchOver between current and new non Live and Live environments
7/ Project Closure
- Closure Report / Sign Off
Resources, Skills and Costs
The estimated total IS Applications project cost is 105 days. To be made up from:
- Project Services: Project Manager, Programme Manager, Portfolio Manager
- Senior Supplier
- Development Technology: Development and Analyst
- Technology Management : Team Manager, Support
- Application Management: Senior User, Support
- Student Systems Partner Development Team Lead & SSP Developer
This figure will be re-estimated after the development phase.
Contingency of 10% has been added at planning to reflect the mandatory deliverables.
Project Governance
Project progress will be reported in line with IS Applications monthly reporting process.
Regular Project Team Progress Meeting will be held to review progress, discuss issues, escalate issues.
Project Stakeholders
| Name | Business Area | Role | Communication Plan | |
|---|---|---|---|---|
| Brandi Headon | Student Systems | Project Sponsor | ||
| Chris Cord | IS Applications | IS Application (Project Team) | ||
| Chris Giles | SSP | Information / Support |
Support / Information |
|
| Defeng Ma | Student Systems Partnership Team Manager | Business Lead / Project Team |
Support / Information |
|
| Franck Bergeret | Student Systems | Programme Manager (Project Team) | ||
| Hannah Johnstone | IS Applications | DevTech (Project Team) | ||
| Heather Larnach | IS Applications | Application Management |
tbc |
|
| Iain Fiddes | Project Services | Senior Supplier | ||
| Peter Jackson | DevTech | Senior Database and Systems Administrator (Project Team) | ||
| Suran Perera | IS Applications | Apps Management (Project Team) |
Support / Information |
|
| Victoria Weinsberg | Project Services | Project Manager (Project Team) |
Project Estimations
| Attachment | Size |
|---|---|
| 52.5 KB |