Project Status Reports

Title Report Date Time Cost Scope Overall Change
June 2018 June 2018 BLUE BLUE BLUE BLUE
April 2018 April 2018 AMBER GREEN GREEN AMBER
March March 2018 RED AMBER AMBER AMBER
February 2018 February 2018 AMBER AMBER AMBER AMBER
January 2018 January 2018 AMBER GREEN GREEN AMBER
December 2017 December 2017 RED RED RED RED
October October 2017 RED AMBER AMBER RED
September 2017 September 2017 RED AMBER AMBER RED
July 2017 July 2017 AMBER GREEN GREEN AMBER
April 2017 April 2017 GREEN GREEN AMBER GREEN
Februrary 2017 February 2017 AMBER AMBER GREEN AMBER
January 2017 January 2017 AMBER AMBER AMBER AMBER
December 2016 December 2016 AMBER GREEN GREEN AMBER
November 2016 November 2016 AMBER GREEN GREEN AMBER
October 2016 October 2016 GREEN GREEN GREEN GREEN
September 2016 September 2016 GREEN GREEN GREEN GREEN
August August 2016 GREEN GREEN GREEN GREEN
June June 2016 GREEN GREEN GREEN GREEN
May 2016 May 2016 GREEN GREEN GREEN GREEN
April 2016 April 2016
April 2016 April 2016 GREEN GREEN GREEN GREEN
March 2016 March 2016 GREEN GREEN GREEN GREEN

Project Info

Project
Student Disability Systems replacement
Code
SAC053
Programme
Student Systems Partnership SSP
Management Office
ISG PMO
Project Manager
Andrew Crossland
Project Sponsor
Sheila Williams
Current Stage
Close
Status
Closed
Start Date
04-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
15-Jun-2018
Programme Priority
2
Category
Compliance

Documentation