June
- Report Date
- June 2016
Achievements in last period
- Workshop and introduction meetings arranged.
Resolved issues
N/A
Open Issues
N/A
Next Steps
- Attend work shops and introduction meeting with stakeholders.
- Complete Foundation.
| Target date | Title |
|---|---|
| 31-Jul-2016 | Foundation complete |
| 31-Oct-2016 | Reassess phase 2 milestones |
| 30-Nov-2016 | Phase 1 Build |
| 08-Dec-2016 | Phase 1: Acceptance signoff |
| 05-Jan-2017 | Delivery 1 Go live |
| 31-Jan-2017 | Phase 2 Foundation |
| 15-Jun-2017 | Phase 2 build Complete |
| 26-Jun-2017 | Phase 2 Acceptance |
| 30-Jun-2017 | Delivery 2 Go live |
| 31-Jul-2017 | Deployment Sign Off Review- DSOR |
| 31-Aug-2017 | Closure |
- Approved budget
- 320.0 days
- Activity this month
- 0.0 days
- Activity this year
- 1.0 day
- Activity to date
- 1.0 day
- Estimate to complete current year
- 2.0 days
- Estimate to complete future years
- 310.0 days