October 2016
- Report Date
- October 2016
Achievements in last period
- Completed thid development Sprint, fourth underway.
- Deployed all development up to end of third sprint to Live.
- Held first workshop for phase two with SDS staff.
- Attended the Disability Review with Gavin Douglas and Jane Norman to discuss the project.
- Began stakeholder analysis to identify members of Coordinators of Adjustment usergroup.
- Met with other key phase two stakeholders in Exams, SDS, Estates
Resolved issues
N/A
Open Issues
N/A
Next Steps
- Continue phase one development.
- Finalise usergroups and representative for phase 2.
- Arrange kick off meeting for phase two.
- Arrange additional workshops for phase 2.
| Target date | Title |
|---|---|
| 08-Dec-2016 | Phase 1: Acceptance signoff |
| 05-Jan-2017 | Delivery 1 Go live |
| 31-Jan-2017 | Phase 2 Foundation |
| 15-Jun-2017 | Phase 2 build Complete |
| 26-Jun-2017 | Phase 2 Acceptance |
| 30-Jun-2017 | Delivery 2 Go live |
| 31-Jul-2017 | Deployment Sign Off Review- DSOR |
| 31-Aug-2017 | Closure |
- Approved budget
- 320.0 days
- Activity this month
- 39.8 days
- Activity this year
- 58.8 days
- Activity to date
- 58.8 days
- Estimate to complete current year
- 261.2 days
- Estimate to complete future years
- 0.0 days