Organisation

Work/Task Breakdown

TaskResponsible
Apply new configuration to config environmentBusiness Lead
Functional Configuration DocumentBusiness Lead
Test new configuration on config environmentBusiness Lead/Pensions team

Business requirements and design document

Business Lead/Software Development
Implementation documentSoftware Development
Software Development (Build)Software Development
Address Jira's including reviewing and re-prioritising at weekly team meetingSoftware Development
Update Oracle 'Pension Information' screenSoftware Development
Decommission old extractsApps Management/Dev Tech

 

Resources Skills and Cost

The resources involved in this project are Payroll and Pensions staff, HR systems, IS Applications: Software dev, Applications Management and Project services with minimal support from Development Technology team

The proposal budget is 50 days, this will be reviewed after the design is complete in August.

The estimate at this stage is 69 days The current JIRAs have been included here 16-Aug-16

Project Team

Pam Baillie Susan McLaren Anne Mathison Manoj Chawli Mike McMonagle Optional attendees

Terry Fox Nikki Stuart Ann Fraser Graham Mechan Anne Finnan Steph Ruthven Emilio Perez Lopez  

Project Info

Project
USS Pension Scheme Changes - Phase 2
Code
PPP008
Programme
Z. Payroll and Pensions (PPP) (closed)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Terry Fox
Current Stage
Close
Status
Closed
Start Date
20-Jun-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Overall Priority
Normal
Category
Compliance