Organisation

Work/Task Breakdown

There are two stands of work in this project, project management and busniess analysis. 

Resources Skills and Cost

20 Apps days

  • 5 days Project Management
  • 15 days Business Analysis

Project Info

Project
MVM Migration To EdWeb and Site Restructure
Code
MVM006
Programme
MVM Business Administration (MVMBUS)
Project Manager
Tim Gray
Project Sponsor
Paul Clark
Current Stage
Close
Status
Closed
Start Date
18-May-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
04-Sep-2015
Programme Priority
2
Overall Priority
Normal
Category
Discretionary