Organisation

Methodology Compliance

 

 

Methodology Stage

Standard Stage Sign-Off

Planning

Approval by Project Manager, Project Sponsor and IS Applications Management Team (WIS)

Business Analysis

Peer Project Analysis Review (PPAR)

System Analysis & Design

Peer Project Design Review (PPDR)

Build

Peer Project Build Review (PPBR)

Integration

Peer Project Integration Review (PPIR)

Acceptance

Acceptance Sign-Off Review (ASOR)

Deployment

Deployment Sign-Off Review (DSOR)

Closure

Closure Review and Approval by Project Manager, Project Sponsor and IS Applications Management Team

 

Resources

Resource Estimates and Costs

 

Estimate

IS Applications Staff Resource

Unknown until analysis stage complete - proposal estimate 200 days, assume that estimate is still appropriate

Support Group Staff Resource

Unknown until analysis stage complete

College Staff and Student Resource

Unknown until analysis stage complete but assumed cost will be low.

Hardware Software and Service Costs

Unknown until analysis stage complete ( see above)

 

Dedicated Project Team?

No.

 

Out of Hours Working

Not expected.

 

  

Additional Information

 

The Sponsor wishes to move away from cash payments entirely but this project will not eliminate cash payments.