Monthly Progress Report
- Report Date
- October 2013
Achievements this period
- Obtained Business Requirements for data required from eFin to be loaded into Corporate Planner
- initial meeting held 9-Oct-13
- initial data received
- further clarifiactions obtained
- Corporate Planner have been accessing the Fec T
Issues
- More work required to support Coprorate Planner
Next steps
- Obtain Business Requirements for data required from eFin to be loaded into Corporate Planner
- initial meeting held 9-Oct-13
- Options to be investigated with estimated
- Support LIVE until Return submitted ongoing
- Agreement of funding agreed - 36 days
Current Milestones
| Date | Stage |
| 06-Nov-2013 | Corporate Planner Data Requirements |
| 14-Nov-2013 | Corporate Planner Data Options |
| 15-Nov-2013 | Technical Design Milestone |
| 25-Nov-2013 | Corporate Planner Review |
| 27-Nov-2013 | Deployment Sign Off and Closure |
- Approved budget
- 36.0 days
- Activity this month
- 9.0 days
- Activity this year
- 36.0 days
- Activity to date
- 37.5 days
- Estimate to complete current year
- 8.5 days
- Estimate to complete future years
- 0.0 days