Weekly update w/c 14/04/14 |
- BIS account changes completed in Dev & Test to reflect the Live environment. This completes the last of the outstanding actions on the completion report.
|
Dawn Holmes |
17-Apr-2014 |
|
Weekly update w/c 07/04/14 |
- Completion report finalised after feedback from sponsor
- Tidy-up tasks in Dev & Test environments complete
- Closure submitted for approval at next week's WIS meeting
|
Dawn Holmes |
11-Apr-2014 |
|
New SITS/Finance Student History Feed |
A new feed has been developed for Finance to allow them to view a full history of students' programmes of study via Business Objects. This helps them to deal with students invoice queries more effectively.
This latest go-live is the final stage of the FIN080 project, which has delivered a number of improvements to the SITS/Finance interfaces to enhance Finance's ability to administer student fees.
Dawn Nicholls
IS Applications Division |
Dawn Holmes |
26-Mar-2014 |
|
Weekly update w/c 31/03/14 |
- Last few technical environment tidy up tasks taking place
- Key Finance business stakeholder is on leave this week but we plan to submit the project for closure as soon as they return next week
|
Dawn Holmes |
04-Apr-2014 |
|
Weekly update w/c 24/03/2014 |
- The issue with SSP access to the new EUGEX views was resolved on Monday by applying a grant script to the live environment
- Deployment review meeting held. Consensus agreement to sign-off the deployment and proceed to close the prject. The group also discussed key lessons learned for inclusion in the completion report
- Draft completion report drawn up & distributed for comment
|
Dawn Holmes |
28-Mar-2014 |
|
Weekly update w/c 17/03/2014 |
- Difficulties securing Dev Tech resource to install the fix for SACS permissions issue on Live. Resource finally secured for next week. Resource also secured to complete the outstanding Jira for tifying up Dev/Test to accurately reflect Live.
- BOXI Universe details handed over to the BI Support Team.
- We still hope to go ahead with the sign-off meeting next week, assuming that the permissions issue is resolved on Monday
|
Dawn Holmes |
21-Mar-2014 |
|
Weekly update w/c 10/03/2014 |
- Go-live of the historic feed took place on Tuesday 11th. This is the last deliverable of the project and after deployment sign-off in 2 weeks time the project will move to closure phase.
- SACS reported post-go-live that they couldn't see the new feed. This is thought to be a permissions issue and a Jira has been raised with Dev Tech.
|
Dawn Holmes |
14-Mar-2014 |
|
Weekly update w/c 03/03/2014 |
- No significant activities this week
- Go-live still planned for 11th March and resources have been secured
|
Dawn Holmes |
07-Mar-2014 |
|
Weekly update w/c 24/02/2014 |
- No significant activities this week
- Go-live still planned for 11th March
|
Dawn Holmes |
28-Feb-2014 |
|
Weekly update w/c 17/02/2014 |
- Acceptance sign off for part 2 (historical feed) took place this week
- Go-live is planned for 11th March so that is doesn't clash with the impending SITS upgrade or the BOXI freeze
|
Dawn Holmes |
20-Feb-2014 |
|
Weekly update w/c 03/02/2014 |
- Re-work has taken place on the final outstanding issue for the historical feed. Unfortuately, although this seems to have resolved the identified issue, another related issue has now been discovered.
- The Acceptance Sign-off meeting and go-live scheduled for next week may now be at risk.
|
Dawn Holmes |
07-Feb-2014 |
|
Weekly update w/c 27/01/2014 |
- Fix for mising domicile narratives went into Test and has been checked by Apps Management
- Outstanding issue passed back by SACS and is being worked on by developer
- Alerts raised and resource secured for go-live on 11th Feb
- Revised estimate approved by WIS (now 233 days)
|
Dawn Holmes |
31-Jan-2014 |
|
Weekly update w/c 20/01/2014 |
- Final changes for the historic feed completed and installed into Test environment for acceptance testing
- Finance requested to re-test the BOXI Universe
- SACS requested to re-test the EUGEX view
- Apps Support requested to check the eFin tables
|
Dawn Holmes |
24-Jan-2014 |
|
Weekly update w/c 13/01/2014 |
- Phase 2 part 1 go-live went ahead as planned on Tuesday (14th). The go-live went smoothly and Apps Management and Finance have confirmed that data was being correctly interfaced.
- A new Jira has been raised for missing 'domicile descriptions' but Finance have agreed that the fix for this can go live with part 2 next month.
- Work is ongoing on the fixes for part 2
|
Dawn Holmes |
17-Jan-2014 |
|
Weekly update w/c 06/01/2014 |
- Sign-off meeting held for Phase 2 - part 1 (debt chasing info and package split) and approval reached for go-live next Tuesday
- Bug fixing ongoing on Phase 2 - part 2 (historic feed)
|
Dawn Holmes |
10-Jan-2014 |
|
Weekly update w/c 16/12/2013 |
- SACS have detected a discrepency in the historical feed data so the go-live planned for this week has been cancelled
- Meeting held with SACS and key IS Apps stakeholders to look at options for progressing the project
- Agreement reached to split phase 2 into two seperate elements: the debt chasing data and the historic feed. Each will go-live seperately.
- New go-live dates agreed for Jan and Feb 2014
|
Dawn Holmes |
20-Dec-2013 |
|
Weekly update w/c 02/12/13 |
- SACS were unable to complete the planned Jira re-testing last week.
- Apps Management has been resourced to undertake integration testing this week. Details of what needs to be tested have been discussed.
- Finance have been reminded of the UAT that they're planned to undertake next week
- The developer is currently updating the implementation plan with rollback information
|
Dawn Holmes |
05-Dec-2013 |
|
Weekly update w/c 02/09/13 |
- Ongoing issue with the inclusion of detailed student applicant data (high level info is ok). A potential solution has been identified but this will incur an additional week of development. PM to speak to Finance to clarify the business requirement as this level of detail may not be a priority.
- Whilst we wait for a decision the developer will remove the latest patch which attempted to insert this detailed information as it has worsened the situation.
|
Dawn Holmes |
06-Sep-2013 |
|
Weekly update w/c 19/08/13 |
- The latest set of fixes for the historical feed have been installed into Test and passed to SACS for testing
- The test BOXI universe has been handed to FIS for testing
|
Dawn Holmes |
23-Aug-2013 |
|
Weekly update w/c 05/08/13 |
- The BOXI universe was handed over to FInance for testing
- The latest set of fixes was installed into Test and passed back to SACS for testing
- The EDUS01/02 screens are on Test ready for FInance to test once SACS has confirmed that the new feed is ok
|
Dawn Holmes |
12-Aug-2013 |