Meeting Notes 2014-Jan-14+16

Meeting Notes  16-Jan-14

Attendees:  Mark D, Anne M, Andy S CC:  David McN, Anne F, Ron

1. This week David M and Dev Tech to review TAD (Week 1) Anne to find out Brian's availability 2. Next week Brian and Tech Man to review TAD (Week 2)  Anne to meet Dougie W and Martin C to discuss their Test Plan for checking out TEST once it has been migrated (Document to prove it is working) 3. Brian and Mark D to set up TEST and prove it is working (week 3) Mark D do Disaster Recover Test 4. Estates Dougie and Martin to TEST Test (week 4 and 5) Mark D on Holiday week 4.

Meeting Notes 14-Jan-14

Attendees:  Mark D, Anne M CC:  David McN, Andy S, Anne F, Ron

Agenda

1. Next Milestones

2. Progress

3. Issues

4. AOB (Any Other Business)

Actions

1. Next Milestone: Design Phase  - (TAD) 29th Jan.

  • Mark has completed his first draft of the TAD.
    • Next to be reviewed by David McN and Dev Tech (16 Jan)
    • Thereafter send to Tech Man and Brian Hunter for review
    • Aim is complete the design phase early so longert for Build Test, given that Mark D on holiday for 1st week in Feb.

2. Test VM Servers Request - went to ITI on Friday 10th Jan for set up. VM Test Servers set up 15-Jan-14

  • Mark D will keep track of it

3. Anne M to check with Brian H to see when he is available in January to wotk with Mark D to build TEST

  • Anne to plan with Brian when he is available
  • Anne to work with Estates to agree TEST plan (i.e. Meterology to work as it currently does on teh new servers, with no functional changes

4.AOB

  • Mark D on holiday 3-10th Feb

Project Info

Project
Meterology Metering System Migration
Code
EST076
Programme
Estates General Programme (EST)
Project Manager
Anne Mathison
Project Sponsor
Geoffrey Turnbull
Current Stage
Close
Status
Closed
Start Date
21-Nov-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
29-May-2014
Programme Priority
5
Overall Priority
Normal
Category
Discretionary