Organisation DRAFT
Work/Task Breakdown (see attached draft )
Work Package |
WP1 - Notifications Service Roll-Out |
WP2 - Notifications from Alma and Card Services |
WP3 - Notification of Timetable Changes |
WP4 - New Notification Subscribers |
WP5 - Notifications from Corporate Systems |
WP0 - Aperero Source Code |
Resources, Skills and Costs
Key Resources by Work Package
Work Package |
LTW Business Lead |
LTW Service Operational Manager |
LTW Service Manager |
Project Manager (shared) |
Business Analyst (shared) |
Apps Development |
Apps Production |
Business Specialists (Subject Matter Experts) |
Specialist Tech Consultant |
WP1 - Notifications Service Roll-Out |
Y |
Y |
Y |
IS Apps |
IS Apps |
ISG & Colleges Team; |
ISG Service Group |
|
Learn, as required |
WP2 - Notifications from Alma and Card Services |
Y |
Y |
Y |
IS Apps |
IS Apps |
ISG & Colleges Team; |
ISG Service Group |
|
Ex-Libris Alma, as required
|
WP3 - Notification of Timetable Changes |
Y |
Y |
Y |
IS Apps |
IS Apps |
USG |
USG & ISG Service Groups |
|
TBC |
WP4 - New Notification Subscribers |
Y |
Y |
Y |
IS Apps |
IS Apps |
ISG & Colleges; Team |
ISG Service Group |
|
Office365 / SMS, as required |
WP5 - Notifications from Corporate Systems |
Y |
Y |
Y |
IS Apps |
IS Apps |
Corporate & Academic Team |
CSG Service Group |
|
TBC |
WP0 - Aperero Source Code | TBC | TBC | TBC | IS Apps | TBC | ISG | Aperero | ||
For Information only WP6 - Notifications from USG Systems |
Y |
Y |
Y |
SSP |
SSP |
SSP |
USG Service Group |
|
SITS StuTalk? |
Project Governance
- Draft Project Structure
- Weekly Core Project Team meetings
- Regular meetings with IS and Corporate stakeholders - Notifications User Group
- Regular meetings with Pilot Users
- Regular update meeting with key DTI Programme Managers particularly DTI Enterprise APIs
- User Centred Portal & Notifications Steering Group - this group meets every 4 / 6 weeks with the following representation from:
- Service Excellence (Barry Neilson, Lisa Dawson, Franck Bergeret)
- DTI (Mark Ritchie, Alison Armstrong, Karen Stirling, Richard Scott)
-
IS Applications (Iain Fiddes)
-
IS Learning, Teaching & Web (Martin Morrey, Melissa Highton)
Project Stakeholders
Name | Business Area | Role | Communication Plan |
---|---|---|---|
Ana Heyn / Adam Wheavil | IS Applications - Application Management | Application Support | |
Bill Lee | IS Applications | Software Development Team Manager | |
Brendan Owers | IS Learning , Teaching & Web | Service Manager / Business Lead - Notifications (w.e.f July 2017) | |
Chris Copner | IS Applications Projects Services | Project Manager (DTI - Enterprise APIs) | |
George Reid | Procurement | Procurement Manager | |
Heather Larnach | IS Applications - Technology Management | Infrastructure Support | |
Karen Stirling | IS Applications - Project Services | Project Manager | |
Karen Stirling | IS Applications - Project Services | DTI - UCP Programme Manager | |
Marissa Warner-Wu | IS Learning, Teaching & Web | Service Operations Manager - Notifications | |
Martin Morrey | IS Learning Teaching and Web | Project Sponsor / Business Lead | |
Michael Sun | IS Applications | Developement Team | |
Richard Scott | IS Applications Projects Services | Project Manager (DTI011 - User Centred Portal Pilot & SAS002 Student Centred Portal Pilot ) | |
Riky Harris / Ewan Scott | IS Applications Development Technology | Technical Architect / Database Administrator | |
Stefan Kaempf | IS Applications Production Management | Senior Supplier | |
Sue Woodger | IS Applications Projects Services | Project Manager (DTI010 - Digital Experience Standards ) | |
Sue Woodger | IS Applications Project Services | Business Analyst | |
Work Package 0 - Aperero Source Code | IS Learning Teachiung and Web / IS Applications | Business Partners for Work Packge 0 |
Key conntacts for this work package are: Martin Morrey Iain Fiddes Bill Lee Development Team - TBC Aperero Contact TBC |
Work Package 1 - Rollout of Notifications Service | IS Applications | Business Partners for Work Package 1 |
Key contacts for this work package for PILOT
|
Work Package 2 - Notifications for Library System Alma & Card Services | Library & University Collections & Card Services | Business Partners for Work Package 2 |
Key contacts for this work package for Alma and Card Services
|
Work Package 3 - Notifications of Timetabling changes | Timetabling | Business Partners for Work Package 3 |
Key contacts for this work package for
|
Work Package 4 - New Notification Subscribers | TBC | Business Partners for Work Package 4 |
Key contacts for this work package are (TBC)
|
Work Package 5 - Notifications for Corporate Systems | Accommodation Services / Finance | Business Partners for Work Package 5 |
Key contacts for this work package for
|
Project Estimations
https://www.projects.ed.ac.uk/unpublished/project/dti020/estimations/planning-estimate-v02
Attachment | Size |
---|---|
![]() | 214.82 KB |