Impact

Priority and Funding

  • This is a Priority 1 project and is sponsor funded by Digital Transformation
  • Days provided from the DTI User Centred Portal Programme are 120 days of which are split across financial years (74 days in 16/17, 46 days in 17/18) following planning exercise budget estimated as overall 320 days.
  • Please note as full business requirements are still to be gathered and prioritised a further re-estimation will be required at commencement of each work package.

Impact and Dependencies

  • This project will deliver to Production developments from WEB010 project
  • There may be dependency on DTI - Enterprise API programme to deliver key API and availability of infrastructure for key work packages.
  • There may be dependency on DTI010 - Digital Experience Standard to receive information to influence notification work packages
  • There may be dependency from / to DTI011 - User Centred Portal Pilot to impact /influence notification work packages
  • There may be dependency from / to SAS002 Student to impact /influence notification work packages
  • Please note that the current version of Notifications Service is aligned to existing MyEd structure and further developments may be required within the DT1011 project to integrate with the  Notifications Service

 

Dependency Diagram

 

Project Risks

Ref Title Impact Probability Risk Status Risk Owner
1 Lack of engagement with Business Partners Major Medium AMBER Open Martin Morrey
2 Lack of engagement with IS areas Major Medium AMBER Open Martin Morrey
3 Availability of key IS Applications Resource Major Medium AMBER Open Karen Stirling
4 Availability of LTW key resource Major Medium AMBER Open Martin Morrey
5 Dependency on Digital Transformation programmes e.g. Enterprise APIs deliverables Moderate High AMBER Open Chris Copner
6 Dependency on Digital Transformation project - check any impact from DTI010 deliverables Moderate Low GREEN Open Sue Woodger
7 Dependency on Digital Transformation project - check any impact from DTI011 deliverables Moderate Medium GREEN Open Richard Scott
9 Dependency on Service Excellence project - check any impact from SAS002 deliverables Moderate Medium GREEN Open Richard Scott
10 Dependency on Service Excellence project - check any impact from SAS005 deliverables Major Medium AMBER Open James Thin
11 Dependency on Service Excellence project - check any impact from Finance Transformation Moderate Medium GREEN Open Karen Stirling
12 Dependency on Core Systems Programme - check any impact to WP5 Corporate Systems (Finance) Moderate Medium GREEN Open Karen Stirling
13 Original development code created as a proof of concept Major Medium AMBER Open Karen Stirling
14 Availability of key development resource Major Medium AMBER Open Bill Lee
15 Dependency on INF121 Migrate Core databses to Oracle 12c Moderate Medium GREEN Open Chris Konczak
16 Publisher integrations may expose data issues within these specific applications Moderate Medium GREEN Open Martin Morrey
AttachmentSize
PDF icon dependencies_dti020_v0.2.pdf119.73 KB