Report for August 19

Report Date
August 2019

Achievements in Last Period

  • Business team signed off on the demonstrations agreeing which suppliers fulfilled the Libraries needs and which didn’t
  • Final report and summary completed
  • PM and Business Lead met with Procurement as to our next steps –meeting notes 29 Aug 2019

Issues

  • Programme Manager has brought in two more members of the Library to sign off report than originally planned for. Due to their circumstances the review meeting has been postponed from 12 August until 4 September
  • Closure date for project is 2 Sep 19 with a milestone for Programme Board approval on but the next programme board is not until 22 Oct 19 – milestone for programme board approval will therefore not be met. PM awaiting decision from sponsor and programme manager whether we close on due date and move milestone for programme board approval into BAU, or extend until after the programme board

Next Steps

  • Review of final report
  • Contact suppliers to inform of next steps
  • Programme board approval
  • Closure - date tbc

Milestones

Options Appraisal

01-Aug -2019

Delivery-Options Appraisal review

12-Aug -2019

Programme board approval

26-Aug -2019

Close

02-Sep -2019

 

Project is Amber as Delivery milestone postponed and we will miss declared closure milestone - new milestones to be submitted to wis when decision made on programme board approval milestone. PM will submit revised delivery and closure milestones together

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Project is Amber as we will miss declared closure milestone - new milestones to be submitted to wis when decision made on programme board approval milestone
Change Status
Has formal escalation taken place?
No
Escalated to
Asked project sponsor and programme manger for decision on closure date
Activity
Approved budget
50.0 days
Activity this month
8.0 days
Activity this year
8.0 days
Activity to date
33.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Digitised Library Workflows Options Appraisal
Code
DLIB001
Programme
Digital Transformation - Digital Library
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Kirsty Lingstadt
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
11-Dec-2018
Planning Date
25-Jan-2019
Delivery Date
30-Sep-2019
Close Date
31-Oct-2019
Overall Priority
Normal
Category
Discretionary

Documentation