Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for October 19 October 2019 BLUE BLUE BLUE BLUE
Report for September 19 September 2019 GREEN GREEN GREEN GREEN
Report for August 19 August 2019 AMBER GREEN GREEN AMBER
Report for July 19 July 2019 GREEN GREEN GREEN GREEN
Report for June 19 June 2019 GREEN GREEN GREEN GREEN
Report for May 19 May 2019 GREEN GREEN GREEN GREEN
Report for April 19 April 2019 GREEN GREEN GREEN GREEN
Report for March 19 March 2019 GREEN GREEN GREEN GREEN
Report for February 19 February 2019 GREEN GREEN GREEN GREEN
Report for January 19 January 2019 GREEN GREEN GREEN GREEN

Project Info

Project
Digitised Library Workflows Options Appraisal
Code
DLIB001
Programme
Digital Transformation - Digital Library
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Kirsty Lingstadt
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
11-Dec-2018
Planning Date
25-Jan-2019
Delivery Date
30-Sep-2019
Close Date
31-Oct-2019
Overall Priority
Normal
Category
Discretionary

Documentation