Closure Report

Project Summary

A previous piece of Business Analysis conducted by IS Apps (ISG012 Sept 2018) highlighted the inefficiencies in the overall Library digitisation process and the requirement to rationalise the processes, storage and provision of digitised content.

From the recommendations in ISG012 this project was to produce an options appraisal to consider what solutions might be available to support the end to end process from ordering of digitisation to provision of digitised items to students, academics and the public.

This project undertook the options appraisal to determine the best way forward, it identified and analysed possible/potential systems to fulfil the different processes and produced high level requirements for measurement of the systems.

The final report for the project was presented to the Digital Library Programme Board on 25 October 

Objectives & Deliverables

The deliverables were prioritised using the MoSCoW prioritisation method

M=Must Have; S=Should Have; C=Could Have; W=Want

Ref

Description

 

Delivered?

Reason for not delivering

Output

O1

To identify measurement to compare systems

 

Yes

 

 

O1D1

Produce requirements as measurement to compare system

M

Yes

 

DLIB001 high level requirements-merged.docx

O1D2

Identify possible / potential systems to investigate

 

M

Yes

 

Initial DAMS investigation DLIB001-dams-investigation.docx

Individual documents on products held in Completed system identification templates

Comparison spreadsheet  - compares the products demonstrated  DLIB001-Report_Matrix.xlsx

Supplier Contact details (for procurement) DLIB001 demonstration list.xlsx

O2

To produce options appraisal

 

Yes

 

 

O2D1

Analysis and options appraisal conducted

M

Yes

 

Final report  DLIB001 Final report.docx

This report was signed off by the Digital Library Programme Board on 25 Oct 19

O2D2

Recommendations from the options appraisal

M

Yes

 

 

 

Success Criteria

Success Criteria as in Project Brief

Delivered

How delivered

An options appraisal and recommendations to support a decision for an improved digitisation solution

Yes

As in deliverables above

DLIB001 Final report.docx

 

 

Benefits

The project will identify the systems that will improve the digitisation processes in the Library. If the recommendations are implemented in future projects the improvements would:

Benefit as stated in project brief

Delivered

Improve the speed of delivery from image capture to online availability

These benefits will be realised when new systems are in place

Allow monitoring of the workflows and enable managers to identify what tasks have been completed and are still to be completed

Dashboard providing overview of progress

Help bottlenecks/issues be identified

Assist with the delivery of management information to allow for estimation of future digitisation projects

 

Analysis of Resource Usage:

Staff Usage Estimate: 50 days

Staff Usage Actual: 49days

Staff Usage Variance:-2%

 

Explanation for variance

 

Cost

Project Brief cost

50d

 

Changes to costs

No changes

 

Actual Cost

49d

 

 

LUC Business lead time = 17.5d

Time

Major Milestones

Project Brief date

Actual Date

Reason

Planning

25-Jan-19

24-Jan-19

 

Delivery  - Options Appraisal

01-Apr-19

19-Aug-19

See PIN notice explanation below

Delivery review

26-Apr-19

15-Oct-19

See PIN notice explanation below. Plus additional sign off brought in on 21/08 delaying the review by another 3 weeks to accommodate them. This was revised to 4 September 19. Then a confusion over processes delayed the report further plus changes to the report had to be accommodated

Programme board approval

14-May-19

25-Oct-19

Due to delays missed the May Board. Next available Board for submitting document was 25 Oct greed project could be closed without this milestone – Project sponsor to take to programme board outside of project

Close

21-May-19

31-Oct-19

Due to delays noted above

 

Issues

PIN process

The project team did market and document analyses of systems that were available but felt they needed more information and asked for demonstrations of the system. We contacted Procurement to see what was possible and they instigated a PIN (Prior Information notice) process (under Procurements Market Engagement strategy) for us which brought in 19 notes of interest. We supplied high level requirements to the interested parties and this reduced the number who wanted to demo to 7. Along with the 6 suppliers identified by project team during market analysis we had 13 demonstrations from 3-29 July 2019 (plus one supplier we were interested in demo’ed separately in September)

The project was extended to take into account the PIN process but we had to wait until replies to the PIN notice were received before we could plan the demonstrations. With the extra time on the PIN process and the physical demos the project was extended by 4 months.

 

Key Learning Points

  • The PIN process was completely unknown to the project team so was not factored into timescales or costs in planning. Business lead setup and executed the supplier demonstrations taking the cost outside of the project. Project manager and business lead should investigate if there are any training opportunities here regarding the procurement process.

Outstanding issues

  • No outstanding issues

Next Steps

  • The final report was approved by the Digital Library Board on 25 Oct 19.
  • From this approval Carla Arton, L&UC Digitisation and Projects Manager, will be considering the outcomes of the project and will be reviewing what services the Library should be offering in relation to digitisation and thereafter will discuss with the Library’s senior management team as to what their service model should be.

Project Info

Project
Digitised Library Workflows Options Appraisal
Code
DLIB001
Programme
Digital Transformation - Digital Library
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Kirsty Lingstadt
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
11-Dec-2018
Planning Date
25-Jan-2019
Delivery Date
30-Sep-2019
Close Date
31-Oct-2019
Overall Priority
Normal
Category
Discretionary

Documentation

Close