Report for April 2015
- Report Date
- April 2015
Achievements this period
- Development iteration 1.3 completed, delivering a number of new features for bio projects (see iteration 1.3 page for further details of functionality delivered)
- Development iteration 1.4 started. Prioritised functionality for this iteration focusssed on radioactivity requirements.
Issues
- Technical issues with Bamboo (our automated deployment tool) meant that completed functionality was not able to be released for UAT
Next steps
- Complete development iteration 1.4
- Start & complete the final development iteration (iteration 1.5)
| Target date | Title |
|---|---|
| 22-May-2015 | End of development iterations |
| 05-Jun-2015 | End of maintenance stage |
| 10-Jul-2015 | Delivery of BI development |
| 24-Jul-2015 | Project closure |
- Approved budget
- 190.0 days
- Activity this month
- 44.4 days
- Activity this year
- 120.1 days
- Activity to date
- 120.1 days
- Estimate to complete current year
- 61.1 days
- Estimate to complete future years
- 0.0 days