Report for April 2015

Report Date
April 2015

Achievements this period

  • Development iteration 1.3 completed, delivering a number of new features for bio projects  (see iteration 1.3 page for further details of functionality delivered)
  • Development iteration 1.4 started.  Prioritised functionality for this iteration focusssed on radioactivity requirements.

Issues

  • Technical issues with Bamboo (our automated deployment tool) meant that completed functionality was not able to be released for UAT

Next steps

  • Complete development iteration 1.4
  • Start & complete the final development iteration (iteration 1.5)

 

 

Target dateTitle
22-May-2015End of development iterations
05-Jun-2015End of maintenance stage
10-Jul-2015Delivery of BI development
24-Jul-2015Project closure

 

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
190.0 days
Activity this month
44.4 days
Activity this year
120.1 days
Activity to date
120.1 days
Estimate to complete current year
61.1 days
Estimate to complete future years
0.0 days

Project Info

Project
RETAIN Enhancements
Code
CSG005
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Dawn Holmes
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
26-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Overall Priority
Normal
Category
Compliance