Report for March 2015
- Report Date
- March 2015
Achievements this period
- Foundations phase completed as planned with User Stories gathered and prioritised
- Technical environment set-up
- First development iteration completed with delivery of the first few Bio User Stories as prioritised by Heahth & Safety
Issues
- Paternity leave of key radiation stakeholder delayed the gathering of the radioactivity requirements
- The business requirement to handle radioactivity aliquots in activity rather then volume is evolving to be much more complex than originally anticipated.
Next steps
- Evaluate impact of activity-based functionality
- Further development iterations
| Target date | Title |
|---|---|
| 04-May-2015 | End of development iterations |
| 29-May-2015 | End of maintenance stage |
| 17-Jun-2015 | Project closure |
- Approved budget
- 190.0 days
- Activity this month
- 56.7 days
- Activity this year
- 74.1 days
- Activity to date
- 74.1 days
- Estimate to complete current year
- 115.6 days
- Estimate to complete future years
- 0.0 days