Weekly update w/c 09/03/15

  • Further estimation meeting held to allocate story points tothe 'must have' User Stories
  • Interation 1 planning meeting held & User Stories selected for first round of development (details at https://www.projects.ed.ac.uk/project/csg005/page)
  • Development for iteration 1 started
  • CF10 migration complete & TAD updated and distributed to support teams
  • CF9 version of application disabled
  • Multiple conflicts received for the developers from other projects (SCE004, STU236, TTU007 & RMAS).  Discussions are ongoing with programme managers, project managers and resource managers on how best to resolve these.  In the meantime the developers are continuing on this project.

Project Info

Project
RETAIN Enhancements
Code
CSG005
Programme
CSG Portfolio Projects (OTHCSG)
Project Manager
Dawn Holmes
Project Sponsor
Candice Schmid
Current Stage
Close
Status
Closed
Start Date
26-Jan-2015
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Jul-2015
Overall Priority
Normal
Category
Compliance