Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for July 2019 July 2019 BLUE BLUE BLUE BLUE No Change
Report for June 2019 June 2019 GREEN AMBER GREEN GREEN Moderate
Report for May 2019 May 2019 AMBER GREEN GREEN AMBER No Change
Report for April 2019 April 2019 AMBER GREEN GREEN AMBER Moderate
Report for March 2019 March 2019 AMBER GREEN GREEN AMBER No Change
Report for February 2019 February 2019 GREEN GREEN GREEN GREEN No Change
Report for January 2019 January 2019 GREEN GREEN GREEN GREEN No Change
Report for December 2018 December 2018 GREEN GREEN GREEN GREEN No Change

Project Info

Project
IDM Database Upgrade
Code
COM045
Programme
ISG - Communication (COM)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Susan Cooke
Current Stage
Build
Status
Suspended
Project Classification
Run
Start Date
11-Dec-2018
Planning Date
18-Jan-2109
Delivery Date
16-Jul-2019
Close Date
09-Aug-2019
Overall Priority
Normal
Category
Compliance

Documentation