Report for June 2019
- Report Date
- June 2019
Achievements in Last Period
- No further progress on project during June due to waiting for the TEST environment to be released from COM043 SOA upgrade project.
- Milestones have been replanned and project re-resourced from the next available COM043 deployment date communicated at the time which is now 09/07/2019.
Issues
- Continuing issues with COM043 have prevented progress with DEV sign off and with the migration to TEST on COM045. A new go-live date for COM043 is now the 09/07/2019. COM045 TEST has been replaned to begin after this date.
- WIS milestone changes has been rejected on 28/06/2018 as there needs to be confirmation of the 27 days carryover into 2019/20 on the project from Head of Production. This has increased from last month as the project has been pushed out further. Head of Production is on annual leave until 22/07/2019.
Next Steps
- DEV sign off
- 2019/20 budget confirmation from Head of Production
- Commence the TEST upgrade
- Begin integration testing
Milestones
| DEV build sign off | 05-Jul-2019 |
| Integration testing sign off | 24-Jul-2019 |
| Acceptance testing sign off | 13-Aug-2019 |
| Deploy to LIVE | 20-Aug-2019 |
| Deployment Sign Off Review | 06-Sep-2019 |
| Project Closure | 20-Sep-2019 |
- Approved budget
- 81.0 days
- Activity this month
- 3.0 days
- Activity this year
- 31.0 days
- Activity to date
- 31.0 days
- Estimate to complete current year
- 22.0 days
- Estimate to complete future years
- 28.0 days