No further progress on project during July due to waiting for the TEST environment to be released from COM043 SOA upgrade project.
Project suspension agreed by Project Sponsor, Programme Manager and agreed at WIS
Proposed restart date: 21/10/2019
Issues
Rollback of the COM043 deployment on 09/07/2019 due to issues with IDM have delayed COM045 proceeding with the TEST upgrade in July. Due to the nature of the issue with COM043 and requiring a suitable deployment window from the business, It is unknown when COM043 will deploy. With the change freeze in September, it has been agreed with Project Sponsor and Programme Manager to suspend COM045 until COM043 can confirm the issues are resolved and a new deployment date is secured
Budget needed for COM045 in 2019/20 is now 47 days. This has not been secured / agreed until a review is completed.
Next Steps
Agree available budget to continue COM045
Review the position of COM043 in October and agree a project restart or extension to the suspension
Restart date is 21/10/2019. Submission to WIS required on 18/10/2019 for restart or to continue suspension.