Report for May 2019
- Report Date
- May 2019
Achievements in Last Period
- No further progress on project during May due to waiting for the TEST environment to be released from COM043 SOA upgrade project.
- Milestones have been replanned and project re-resourced from the next available COM043 deployment date communicated at the time which was 11/06/2019.
Issues
- Continuing issues with COM043 have prevented progress with DEV sign off and with the migration to TEST on COM045. The project had been replanned and resourced to start after 11/06/2019. COM045 PM is waiting on confirmation that SOA will be deployed on 11/06/2019 before submitting the milestone changes to WIS, or to replan COM045 if a new deployment date is confirmed.
- The project will carryover into 2019/20. Current estimate is 8.5 days
Next Steps
- DEV sign off
- Commence the TEST upgrade
- Begin integration testing
Milestones
| DEV build sign off | 14-Jun-2019 |
| Integration testing sign off | 02-Jul-2019 |
| Acceptance testing sign off | 22-Jul-2019 |
| Deploy to LIVE | 01-Aug-2019 |
| Deployment Sign Off Review | 15-Aug-2019 |
| Project Closure | 29-Aug-2019 |
- Approved budget
- 81.0 days
- Activity this month
- 3.0 days
- Activity this year
- 28.0 days
- Activity to date
- 28.0 days
- Estimate to complete current year
- 43.0 days
- Estimate to complete future years
- 8.5 days