Overview

Background

The current solution used to manage the Accommodation Catering and Events Delivered Catering service does not meet the business requirements, and having been advised by the supplier of the current solution that the product will no longer be developed, there is now the requirement to procure a replacement solution that will deliver the specified business requirements. 

 

Scope

The scope of this project will be to define the business requirements required in a new Delivered Catering solution.  In compiling this functionality, there will be the requirement to;

  • Ensure that these can be fully accommodated within the new core Finance system via an appropriate interface, and this will require consultation with the core Finance team
  • Consider the impact and requirements of Single Sign On (SSO) via EASE

In addition;

  • The technical requirements will be defined by referring to the current IS Procurement Question Set.  In compiling the appropriate questions, the ACE technical Lead will lead the IT Procurement questions with assistance from colleagues in both Applications Directorate and Information Security.  
  • The Accessibility requirements will be defined and subsequently reviewed by the ISG Disability Officer.

Given the available budget for the contract, the procurement route will follow ‘Route One’ of the Universities Procurement guidelines that requires a minimum of three quotations to be sought from different suppliers that will deliver the specified business and functional requirements  

The implementation of any procured solution will be out of scope of this project and be delivered via a follow-on project, during which an Equalities Impact Assessment (EqIA) will also be completed.

 

Objectives

Priority – M = Must Have; S = Should Have; C = Could Have; W = Want 

  • M = has to be satisfied for the final solution to be acceptable in terms of delivery dates, compliance, viability etc. 

  • S = high-priority requirement that should be included if possible -workarounds may be available 

  • C = a nice-to-have requirement 

  • W = want but will not be part of this project 

  • O = Objective 

  • D = Deliverable 

Ref. Objectives and Deliverables Priority Owner
O1 Specify Business Requirements     
D1.1 Document business requirements  M Business Lead
O2 Complete relevant GDPR checks    
D2.1 Produce  a Data Protection Impact Assessment (DPIA) M Project Team 
O3 Undertake Procurement Process    
D3.1 Prepare ITQ M

Business Lead / ACE Technical Lead

D3.2 Market Research M Business Lead
D3.3 Issue ITQ M Business Lead
D3.4 Review Supplier Responses M Project Team
O4 Award Contract     
D4.1 Raise Purchase Order  M Business Lead 

 

Benefits

  • The procured solution will lead to enhance the service offered through Delivered Catering through

    • Improved Service Delivery
    • Full utilisation of new Core Finance System
    • Improved customer experience
  • Delivery of a specification of requirements which can used as living document to review on-going functional requirements  

  • Compliance with recommended procurement processes within the University  

 

Success Criteria

The project will be considered a success on the successful delivery of the following 

  • Delivery of a specification of requirement 

  • Compliance with recommended procurement processes  

  • Full audit of procurement process 

  • Ability to enable full integration with Core Finance system  

  • Ability to implement SSO

Project Milestones

Stage Milestone  Due Date 
Plan Planning 20/09/19
Execute  Analysis 18/10/19
Execute Issue ITQ 04/11/19
Execute Close ITQ 29/11/19
Execute Award Contract 17/01/20
Execute Conclude Contract 14/02/20
Close Close 28/02/20

 

Project Info

Project
Delivered Catering Procurement
Code
ACS042
Programme
Accommodation Catering and Events (ACE)
Management Office
ISG PMO
Project Manager
Andrew Stewart
Project Sponsor
Ian Macaulay
Current Stage
Initiate
Status
In Progress
Project Classification
Run
Start Date
30-Aug-2019
Planning Date
20-Sep-2019
Delivery Date
14-Feb-2020
Close Date
28-Feb-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation

Plan